Beacon Street
| June 16, 2005
| We were informed of a new case of underpinning at the Mass. College of Optometry at 416-430 Beacon St. Pilings in this multiple building property have been cut off at four different heights, with the higher cut off pilings failing. Also on Beacon, the well at the corner of Dartmouth where BWSC repaired their manhole showed a reading that was up about two feet from the prior reading before the repair. Farther down on Beacon St, the well in front of 166 shows an even lower reading than before. This well and others nearby showed day to day fluctuations (sometimes within a few hours) of over a foot. |
| July 19, 2005
| John Sullivan reported back after his crew was able to get a video camera into the sewer in front of 166 Beacon St, where we have recorded very low levels. While they couldnt see actual inflow, the condition of the sewer was such that they will be looking for funding to line it from Brimmer St to Dartmouth. |
|