303 Columbus Avenue

October 26, 2006 I met with the contractor for the project to agree on the location of an observation well that they will install in front of the neighboring building at 321 Columbus Avenue. Many of the neighbors have expressed concern about the possibility of piling damage from construction of this new building. The hope is that that the well will be in before they begin dewatering for construction.
January 18, 2007 The wells that the project is monitoring don’t show any negative impacts on groundwater levels. They expect to install the monitoring well in front of 321 Columbus Avenue this week.