Public Improvement Commission

January 18, 2007 I reviewed a draft of the PIC’s regulations for recharge systems under public ways. They looked very reasonable. I would expect them to be adopted shortly.
February 15, 2007 The PIC adopted its rules for recharge systems extending under public ways this morning. The rules require that an applicant only use the public space if he cannot install a system on his own property and set requirements for avoiding interference with existing or potential infrastructure.
December 21, 2009 I attended an informal discussion in front of the PIC about the recharge system proposed to be constructed as part of the project to add two buildings to the Prudential Center. PIC will have jurisdiction because the recharge galleys will be on public property.