Hello everyone. The following summarizes our work from 9/20/05 - 10/03/05:

  • Completed contract for the installation of for 114 wells.
  • Obtained building permit and parking permits for the next group of 180 wells to be installed.
  • Started contract of 180 wells. Have installed 13 of the 180 wells so far.
  • Updated database to include all new o.w.’s that have been installed.
  • Continued readings for the fall 2005 period.

I will continue to be both in the field and the office coordinating the overall activities.