Hello everyone. The following summarizes our work in the week ending 7 May 2004.
- 10 observation well locations have been cored and vacâed. These wells are scheduled to be installed next week 10-14 May 2004. Four of the proposed locations must be moved and dig-safed. Various attempts were made on all four proposed locations and were unsuccessful.
- At the last minute, Alex Marinkovich decided to take another summer co-op leaving us only with Derek Barnes. Derek is still scheduled to start on 17 May 2004. The search continues for an additional co-op.
- I will continue to be in the field coordinating the overall activities. If you have any questions please feel free to contact me.
Kind Regards,
Christian Simonelli
BGwT Technical Coordinator/Environmental Engineer
222 Newbury Street
Boston, MA 02116
Tel: 617.886.7553
Fax: 617.886.7600
CSimonelli@HaleyAldrich.com
bostongroundwater.org